Posts By: Gregory Cokinos

Important Changes to 2017 AIA Contract Forms

Recently, the American Institute of Architects (“AIA”) published its decennial update to the AIA forms most commonly used by contractors, owners, and design professionals. In total, AIA updated fourteen of its construction contract forms, including the industry-standard Owner-Contractor forms, such as the A101 – A105 base contracts and A201 General Conditions, as well as the Owner-Architect forms in the “B-series” of documents (i.e., B101 – B105). Due to their preeminence among the AIA suite of documents, some of the more important changes to the A101, A102, and A201 construction documents are discussed below. If you have any questions or need additional information, please contact David Tolin or John Warren at Cokinos|Young.

A101 and A102
The AIA A101 and A102 forms are the long-form construction contracts intended for use between Owners and Contractors. The 2017 changes are very similar across these two documents, though the different billing methods (i.e., cost-plus vs. lump sum) lead to some slight differences. The important changes to both documents are:

  • Contract Time. Both documents now adopt a menu-style approach to designation of the Commencement Date and the date for Substantial Completion. Contracting parties can select from a variety of options for the start date of the work, including date of execution, upon receipt of a notice to proceed, or some other date, and they can also now select between a date-certain for completion of the work or a specified number of calendar days. If the parties have agreed upon interim dates for partial completion of certain aspects of the work, the forms also now include a provision for express milestone dates (A101 §§ 3.1 – 3.3; A102 §§ 4.1 – 4.3).
  • Liquidated Damages. Whereas liquidated damages were limited to a parenthetical reference in the 2007 forms, the 2017 documents now include two express provisions addressing liquidated damages. In substance, this is not a significant change, but in practice it may lead to a heightened focus on liquidated damages during the contract negotiation phase of projects. The original, parenthetical reference was more discrete and could be easily overlooked or ignored, while the new clauses may need to be negotiated and modified as needed (A101 §§ 3.33 and 4.5; A102 §§ 4.33 and 5.1.6).
  • Cost of the Work. Articles 7 and 8 of the A102 define what costs incurred by the Contractor will be reimbursable as a “Cost of the Work.” The AIA 2017 update tweaks some of the language in these articles, but the majority of the changes are inconsequential. One important change is certain types of Contractor-employee compensation (e.g., bonuses, incentives, etc.) are moved from Article 7 to Article 8, removing them from the list of reimbursable costs. Also, there is now an express presumption that labor costs will not increase during the course of the project (A102 § 7.2.5). Perhaps offsetting these changes, self-insurance and captive insurer costs are now included as reimbursable Costs of the Work (though Owner approval is required) (A102 § 7.6.1.1).
  • Payment Procedures. The provisions addressing payment procedures were significantly overhauled in both documents. AIA claims the new payment provisions are “simplified,” and for the most part they are. The new language is clearer and more concise, due in no small part to the decision to separate retainage language into its own section. The payment provisions now set forth a list of all items to be included in calculation of each payment, followed by a list of all items that should be deducted. In general, this is an improvement, but Contractors should be aware the list of items to be deducted from every pay application includes “any amount for which the Contractor does not intend to pay a Subcontractor or material supplier, unless the Work has been performed by others the Contractor intends to pay” (A101 § 5.1.6.2.3; A201 § 12.1.7.2.3). This language, formerly contained in the A201 General Conditions (at § 9.3.1.2), appears to prevent a General Contractor from seeking progress payments for self-performed work or overhead and profit. This language may be problematic, especially in light of its new placement as a specified deduction in the primary payment provisions of the A101 and A102.Retainage is now addressed in separate provisions (A101 § 5.1.7; A102 § 12.1.8), which is an improvement. However, both the A101 and A102 now provide for retainage billing upon substantial completion (A101 § 5.1.7.3; A102 § 12.1.8.3), which is at variance with Owner-obligations under Texas law. Because Owners are required to withhold retainage until at least thirty days after Final Completion of a project, this language should be revised or adjusted unless other accommodation is made for the protection of subcontractors and suppliers (e.g., bonding of the project).As noted above, the 2017 AIA updates treat the A101 and A102 somewhat differently due to their distinct billing methods (cost-plus vs. lump sum). The 2017 A101 now requires the Owner to pay the contract price “allocable to the work,” while references to percentages of completion and the schedule of values are eliminated from the calculation of payments (A101 § 5.1.6.1). Conversely, the 2017 A102 retains these references and adds some safeguards and cost controls for the protection of the Owner. For example, all costs that must be approved by the Owner must now be approved in writing prior to incurring the cost (A102 § 7.1.2), and the GMP must now be separately allocated to each portion of the work, including the contingency and the Contractor’s Fee (A102 § 12.1.5). Additional language was also added to address refinement and development of the Contract Documents after approval of the GMP (A102 §§ 5.2.5, 5.2.6).
  • Termination for Convenience. The 2007 forms provided for recoupment by the Contractor of overhead and profit for work not yet completed in the event of a termination by the Owner for convenience. The new forms replace that compensation with an agreed “Termination Fee” whenever the Contractor is terminated for convenience. Parties will now need to agree in advance what this Termination Fee would be.
  • Insurance. Insurance provisions for the A101 and A102 documents were previously comprised simply of a reference to the A201 General Conditions, which contained detailed insurance requirements in its Article 11. For the 2017 forms, the insurance provisions have been combined into a single, comprehensive insurance and bonds exhibit, to be attached as Exhibit “A” to either the A101 or A102 (the “short-form” contracts, such as the A104 and A105, continue to include insurance provisions in the main body of the contract). The insurance and bonds exhibit uses a checkbox system, offering various insurance options the parties can select from during the contract negotiation phase. This change reflects the common practice in the construction industry of creating separate insurance exhibits for each new construction contract.
  • Electronic Data and Building Information Modeling. The new forms continue to emphasize the AIA E203-2013 Building Information Modeling (BIM) and Electronic Data Exhibit and insert additional clauses pertaining to use of that Exhibit (A101 § 9.1.4; A102 § 16.1.4; A201 §§ 1.6 – 1.8). Of particular note, where notice is required by the Contract Documents, the notice will be sufficient if delivered in accordance with the Electronic Data Exhibit. This could potentially lead to disputes over informal e-mails serving as proper notice, though the 2017 A201 still requires claims for additional money or time to be in writing and delivered by certified mail or courier with proof of delivery (A201 § 1.6.2).

A201
The AIA A201 form is the comprehensive “General Conditions” document for both the A101 and A102 base contract forms. Some of the important changes to the A201 are:

  • Owner’s Financial Information. The requirements and obligations of the Owner to provide details regarding its financial arrangements for the project are now more comprehensive, and there are now provisions allowing the Contractor to refuse to proceed or to suspend work in the event the Owner fails to provide the required information (A201 § 2.2.2).
  • Means and Methods. Where the Contractor determines specified means and methods to be unsafe, the Contractor previously had some protection because the 2007 A201 required the Architect to investigate and relieved the Contractor of responsibility if directed to proceed with Owner-required means and methods it deemed unsafe. In the 2017 A201, the Contractor is now required to propose alternate means and methods (rather than simply wait on the Architect for instruction) and proceed with those alternate means and methods unless the Architect objects to the proposed alternative. While this seems like a more pro-active approach, the result is a bit murky. What happens if the Architect does object? The 2017 A201 does not answer that question (A201 § 3.3.1).
  • Warranties. All material, equipment, and other special warranties must now be issued in the name of the Owner or made transferable to the Owner (A201 § 3.5.1).
  • Schedule. The Contractor is now required to include more information in its schedule submittal, including schedule milestone dates, apportionment of the work by construction activity, and the time required for completion of each portion of the work (A201 §3.10.1).
  • Owner-Contractor Communication. Direct communication between the Owner and Contractor is now expressly authorized (as opposed to all communication being routed through the Architect, which was the 2007 standard). However, the A201 still requires that the Architect be kept informed of all project-related communications (A201 § 4.2.4).
  • Changes. When the Contractor disagrees with whether a proposed change is a “minor change,” and believes the change will affect the Contract Sum or Contract Time, the Contractor can now refuse to perform the change until the disagreement is resolved or a Construction Change Directive is issued (A201 § 7.4).
  • Liens. Lien waivers and releases from subcontractors must now be submitted with each Application for Payment (A201 § 9.3.1). If the Owner pays all amounts due as obligated under the contract, the Contractor must now indemnify and defend Owner against any lien claims or claims for payment by Subcontractors (A201 § 9.6.8). These changes reflect fairly common practices among sophisticated Owners in the construction industry.
  • Termination by Contractor. Termination of the contract by the Contractor (for cause) now entitles the Contractor, in addition to previous remedies, to overhead and profit on the work not yet executed at the time of termination (A201 § 14.1.3).
  • Termination for Convenience. As with the A101 and A102, the A201 now assumes the Contractor will be paid a Termination Fee for any convenience termination by the Owner (A201 § 14.4.3).
  • Dispute Resolution. A new timing mechanism was added to prevent mediated disputes from becoming stale. After the Initial Decision Maker has decided a disputed matter and that matter has been mediated, either party may demand that the other party file its claim in either arbitration or litigation. If the other party does not file a claim within 60 days of the demand, then both parties waive their rights to arbitration or litigation, and the initial decision becomes final (A201 § 15.3.3).

This is not intended to address every change made to the documents discussed, nor is it intended to constitute legal advice.

David Tolin is an Attorney in the Houston office of Cokinos|Young. His bio is available here and he may be reached directly at 713-535-5518.

John Warren is a Principal in the Houston office of Cokinos|Young. His bio is available at here and he may be reached directly at 713-535-5577.

Policyholders Beware: Convergence of New Texas Insurance Laws and Hurricane Harvey

In a bizarre twist, the insurance legislation originally billed as the “Hailstorm Bill” will likely have the greatest effect not on hailstorms, but on the most significant flooding event in Texas history. As Hurricane Harvey continues to deluge the Texas Coast, Texas Insurance Code Section 542A is set to take effect at 12:01 AM on Friday, September 1. Originally drafted as a response to the high volume of hail litigation in Texas, the new law now specifically applies to property damage resulting from all “forces of nature,” including hail, rain, floods, hurricanes, tornadoes, wind, etc.

The new law makes several changes to the remedies of property owners under the Texas Insurance Code. Most significantly, the law: (1) reduces penalties faced by insurance companies who wrongfully deny or delay payment of claims; and (2) creates complex notice requirements, which, if navigated incorrectly, potentially reduce the amount of attorneys fees the insured can ultimately recover from the insurance company.

Specifically, newly added Section 542.060(c) will reduce the statutory penalty for delayed or unpaid claims from 18% to a rate determined by a market-based formula, which is capped at 20% but would currently be only 10%. This section applies only to “claims” filed after September 1, 2017. So clients facing the certainty of a property damage claim resulting from Harvey should immediately report these claims to their insurance carrier (by August 31, 2017) and keep records of what was sent and when.

In the event that litigation becomes necessary, the law also requires a claimant to provide its insurer with written notice 61 days before a lawsuit can be filed. The notice must provide specific details, including “acts or omissions” leading to the claim, the dollar amount owed, and the reasonable and necessary attorney fees already incurred. In a potential pitfall for property owners, the recoverability of attorneys fees is now conditioned on the amount demanded in this original notice. Specifically:

  1. If the insured prevails at trial and the jury awards 80% or more of the original demand, attorneys fees are recoverable in full.
  2. If the insured prevails and the jury awards 20% or less than the original demand, no attorneys fees will be awarded.
  3. If the jury award is in the 21-79% range, attorneys fees are pro-rated.

Unfortunately, this new portion of the law applies to all “actions” (as distinguished from “claims”) filed after September 1, 2017—meaning that unless insureds have already given the required written notice and are ready to file a lawsuit—the new law will likely apply. Thus, almost all litigation arising out of Harvey will be governed at least partially by this new law.

Policyholders will want to consult counsel in order to maximize their rights and recoveries. Feel free to contact us if you have any questions or if we can help in any way.

Pat Wielinski to Speak at IRMI Construction Risk Conference in November

The 37th IRMI Construction Risk Conference (CRC) will be held in Indianapolis, Indiana from November 5th to the 8th this year. This conference brings nearly 2,000 leading project owners, general contractors, subcontractors, developers, insurers, and insurance agents and brokers together to explore and convey state-of-the-art ideas and techniques for improving construction insurance coverage, controlling insurance costs, and fine-tuning risk management programs.

Pat Wielinski will be speaking on November 6th during the 10:45am-11:45am session on the topic of “Lessons Learned: Where CGL and Professional Liability Policies Collide,” a complex claim study. He has been a presenter at this conference since 1984 and has spoken nearly 20 times since.

For more information on the conference, here are some important links:
Conference Home Page
Conference Agenda
Register to Attend

ABC Central Texas Meet the Contractors

Cokinos | Young recently sponsored the Associated Builders and Contractors – Central Texas Chapter Meet the Contractors at the Norris Convention Center in Austin. Congratulations to State Representative Paul Workman for receiving the 2017 ABC Texas Legislative Award and to Councilman Ellen Troxclair for receiving recognition for her work in Austin.

 

After the Flood: Hurricane Harvey’s $180 Billion Impact on Houston’s Economy

The destruction from Hurricanes Harvey, Irma, and Maria is virtually unprecedented. In fact, Harvey and Irma are the only Category 4 storms to hit the U.S. in the same year (let alone the same two-week span), and Maria made landfall in Puerto Rico as a Category 4 storm as well. The 100-plus mile-per-hour winds are bad enough, but the flooding in the areas hit by these storms reached near-Biblical proportions. Hurricane Harvey managed to dump 27 trillion gallons of water on Texas and Louisiana; parts of Houston received nearly 53 inches of rain during that time.

It’s no surprise that local residents have found themselves in desperate need of help, especially when it comes to rebuilding their homes and businesses. The Houston Builders Association estimates that 30,000 homes in the city were damaged. In addition, approximately 200,000 homes throughout the state of Texas will need to be repaired or rebuilt. And unfortunately, these “acts of God” are often not covered under standard homeowner’s insurance policies.

RMS, a catastrophe modeling company, estimates that $25 to $35 billion of the damages caused by Hurricane Harvey will be covered by insurance. However, the total amount of economic damage — which includes uninsured losses — may reach $70 to $90 billion. That means contractors and construction firms will be more in-demand than ever, but many contractors may find themselves in trouble following these types of disasters, too.

Although events like these may be difficult to predict, there are certain things contractors can do to protect themselves from storm damage during and following the construction process. By working with a construction lawyer to include force majeure provisions in contracts and investing in builder’s risk insurance, business owners and independent contractors will often safeguard their investments in calamitous situations.

Considering that the cost of cleanup from Harvey may eventually reach $180 billion, preparation and prevention is clearly the best way to go, particularly if you conduct business in locations that are prone to significant storm damage. While you may not be able to stave off the actual storm, including construction law components in contracts and purchasing better insurance policies may keep your business or home from going under.

Best Lawyers© Announces 2017 List & Includes Three Attorneys from Cokinos | Young


First published in 1983, Best Lawyers© is the oldest and most highly respected peer review guide to the legal profession worldwide.  Selection to this prestigious list is based on exhaustive evaluations in which leading attorneys cast votes on the legal abilities of other lawyers in their geographical and legal practice area.

Three attorneys from Cokinos | Young have been selected for inclusion in the 2017 edition of Best Lawyers in America©. Cokinos | Young is proud to recognize the following attorneys for their continued commitment to excellence in their profession and practice areas.

HOUSTON

Gregory M. Cokinos
Construction Law, Litigation/Construction
Mr. Cokinos has appeared on this list for more than 10 years.

Parker Fauntleroy
Personal Injury Litigation/Defendants

DALLAS/FORT WORTH

Patrick J. Wielinski
Insurance Law, Litigation/Construction
Mr. Wielinski has appeared on this list for more than 5 years.

2017 ABC South Texas Chapter Excellence in Construction Awards Banquet

The Associated Builders and Contractors – South Texas Chapter held its 25th Silver Anniversary of the Excellence in Construction Awards Banquet at the Omni San Antonio Hotel at the Colonnade on August 3, 2017. Cokinos | Young is honored to be a Platinum Sponsor of the South Texas Chapter and congratulates all of the award winners.

Cokinos | Young is the Platinum Sponsor of the 5th EPC Contract & Risk Management Conference

The 5th EPC Contract & Risk Management Conference will be held in Houston, Texas from September 12th to September 14th. The conference is focused on “Maximizing Stakeholder Cohesion and Collaboration through Project Lifecycles to Mitigate Risk and Optimize Organizational Outcomes” and aims to help construct successful projects through lessons learned in drafting, negotiating, formulation, insurance coverage, and execution.  Cokinos | Young is proud to be the Platinum Sponsor for this year’s conference.

Pre-Conference Workshops start on September 12th followed by two days of presentations, joint discussions, and interactive panel discussions. The conference provides up to 16 CLE credits for attendees.

For more information, click here to download the agenda.

Venue Name:
Sheraton Suites Houston Near the Galleria
Address: 2400 West Loop South, Houston, TX 77027
Phone: 713-586-2444
Website: http://www.sheratonsuiteshouston.com

Just Another Day at the Office

It is just another day on the job for the team at Cokinos | Young. Shelly Masters and Natalya Sheddan out of our Austin office led a one week inspection in a case involving one of the largest privately held commercial general contractors alongside a 20 person subcontractor crew, a dozen experts, two aerial boom lifts, one drone and a selection of construction lawyers.

The Spill Magic Saga Continues – Austin v. Kroger Is Back

Houston | San Antonio | Austin | Dallas/Fort Worth

 

On June 2nd, the Fifth Circuit designated its opinion in Austin v. Kroger, L.P., 2017 WL 1379453 (5th Cir. Apr. 14, 2017) for publication. In that opinion, the Fifth Circuit yet again remanded Randy Austin’s lawsuit against his former employer, Kroger Texas, L.P., to the United States District Court for the Northern District. In doing so, the Fifth Circuit (1) limited the court’s role in determining what is and is not a “necessary instrumentality”; and (2) narrowed the application of the “customary work” defense, under which an employer cannot be held liable if the injury results from performing the same character of work that employees in the plaintiff’s position have always done. The Fifth Circuit also held that the Northern District incorrectly applied a more stringent standard to Austin’s motion for reconsideration of the exclusion of Austin’s untimely expert report on causation. Under the proper, more lenient, standard the Fifth Circuit held the expert report should have been considered. The holding is a double-whammy for nonsubscribing employers. It makes it harder, as a legal matter, for nonsubscribing employers to obtain summary judgment on two critical defenses, while simultaneously making it easier for injured employees to overcome summary judgment by augmenting the summary judgment record with new evidence.

By now, nonsubscribing employers are quite familiar with facts of this case. In July 2009, Austin was on the job as an employee of Kroger at a Mesquite, Texas location when he slipped and fell while mopping a brown oily liquid from a restroom floor. Austin alleged that for this task he would normally use a product called “Spill Magic,” which Kroger’s safety manual recommended for cleaning up liquid spills. But on the date of the accident, there was no Spill Magic available. After a long and winding procedural history that involved multiple motions for summary judgment and a stop through the Texas Supreme Court, Austin’s only remaining negligence theory was that Kroger breached its duty to provide Austin with a “necessary instrumentality” (i.e. Spill Magic) for the safe performance of his job.

In April 2016, the Northern District of Texas granted summary judgment for Kroger on the remaining “necessary instrumentality” claim and denied Austin’s motion for reconsideration of the district court’s previous denial of Austin’s motion for leave to file a surreply to Kroger’s motion for summary judgment.

The district court granted summary judgment on two grounds. First, the district court ruled that Kroger had “no duty to provide an unnecessary instrumentality.” Because there was evidence that Austin had previously performed this same task safely using a dry mop (which was available on the date of the accident), the court reasoned Kroger had no duty to provide Spilll Magic. This holding is an extension of the principle, under Texas law, that an employer need only provide a reasonably safe method to perform the duties of employment, not the “best and safest” way.

The Fifth Circuit’s opinion, however, seems to call this principle into question, at least insofar as it can form the basis for summary judgment. In the Fifth Circuit’s opinion, whether the Spill Magic was a necessary instrumentality presented a “genuine issue of material fact” for the jury to decide. The Fifth Circuit opined that Kroger (and by extension the district court) placed “undue emphasis” on the fact that Austin had previously used the dry mop to clean up a “much smaller” spill. Thus, while the Fifth Circuit acknowledged that “the existence of a legal duty is a question of law for the court to decide,” the Court stopped short of making a case-specific determination of the extent of that duty. In other words, the Fifth Circuit seems to be saying that while the court can decide that there is a duty to provide necessary instrumentalities, whether a specific instrumentality is “necessary” is a fact question.

The district court also granted Kroger’s motion for summary judgment on the basis that Austin’s “injury occurred while he was performing his customary work duties.” The Fifth Circuit, however, disagreed, holding that an employer does have a duty to provide instrumentalities necessary for the safe performance of the employee’s customary work. This holding seems to limit the application of the “customary work” defense to situations where an employee is injured while performing his usual job duties, and there is no independent breach of a duty (such as the duty to furnish necessary instrumentalities).

Finally, the district court had previously denied leave to Austin to supplement its summary judgment briefing with an expert report that linked Austin’s injuries and medical expenses to the slip and fall. In the April 2016 opinion, the district court declined to reconsider that ruling. The Fifth Circuit, however, held that the district court abused its discretion in preventing Austin from introducing the expert report. The Fifth Circuit reasoned that the District Court erroneously relied upon Federal Rule of Civil Procedure 59(e) in denying reconsideration, instead of relying on the more lenient Federal Rule of Civil Procedure 54(b). Because of this abuse of discretion, the Fifth Circuit vacated that portion of the district court’s order and remanded the matter to the District Court for reconsideration of Austin’s argument under the correct Rule and standard.

 


Travis M. Brown
tbrown@cokinoslaw.com
817-635-3619

Roland F. Gonzales
rgonzales@cokinoslaw.com
210-293-8740

This website uses cookies to improve your experience. By using our site, you provide your consent.

Read More